November 10, 2026
We have new floors! Concrete pouring is complete throughout the basement and the first two rounds of polishing will begin at the end of this month once the concrete has had time to cure. A small gap around the base of the brick pier was left and will be filled in with a thin layer of concrete, gravel and then an epoxy resin. This will allow visitors to see how the telescope pier was originally designed to be separate from the building so that vibrations wouldn't skew telescope findings.
Until polishing begins at the end of the month, there’s no other work scheduled. After concrete polishing, structural repairs will begin. This includes the replacement of 3 window headers, a few joist repairs, and masonry tuckpointing. Once structural work is complete, framing of new walls will begin and installation of new windows. We are excited to see the renovated spaces take their new shape!